The Defense Waste Processing Facility, from Vision to Reality

The Defense Waste Processing Facility, from Vision to Reality
Author:
Publisher:
Total Pages: 5
Release: 2000
Genre:
ISBN:

When the Savannah River Plant began operation in the early 1950's producing nuclear materials for the National defense, liquid, highly radioactive waste was generated as a by-product. Since that time the waste has been stored in large, carbon steel tanks that are buried underground. In 1960 one of the tanks developed a leak, and before recovery measures could be taken, about 25-gallons of radioactive salt solution had overflowed the secondary liner and seeped into the soil surrounding the tank. Significant improvements to the tanks were made, but constant surveillance was still required. Thus, the opinion began forming that storage of the mobile, highly radioactive waste in tanks was not a responsible long-term practice. So in the late 1960's the Savannah River Laboratory began research to find a suitable long-term solution to the waste disposal problem. Several alternative waste forms were evaluated, and in 1972 the first Savannah River waste was vitrified on a laboratory scale. By the mid-1970's, the DuPont Company, prime contractor at the Savannah River Plant, began to develop a vision of constructing America's first vitrification plant to immobilize the high level radioactive waste in borosilicate glass. This vision was later championed by DuPont in the form of a vitrification plant called the Defense Waste Processing Facility (DWPF). Today, the DWPF processes Savannah River High Level Waste sludge turning it into a solid, durable waste form of borosilicate glass. The DWPF is the world's largest vitrification facility. It was brought to reality through over 25-years of research and 13-years of careful construction, tests, and reviews at a cost of approximately $3 billion dollars.

Design and Construction Innovations of the Defense Waste Processing Facility

Design and Construction Innovations of the Defense Waste Processing Facility
Author:
Publisher:
Total Pages: 14
Release: 1990
Genre:
ISBN:

Construction of the Defense Waste Processing Facility (DWPF) at the Savannah River Site (SRS) is essentially complete. The facility is designed to convert high level radioactive waste, now contained in large steel tanks as aqueous salts and sludge, into borosilicate glass which will solidify in stainless steel canisters. All processing of the radioactive material and operations in a radioactive environment will be done remotely. The stringent requirements dictated by remote operation and new approaches to the glassification process led to the development of a number of first-of-a-kind pieces of equipment, new construction fabrication and erection techniques, and new applications of old techniques. The design features and construction methods used in the vitrification building and its equipment were to accomplish the objective of providing a state-of-the-art vitrification facility. 3 refs., 10 figs.

Defense Waste Processing Facility

Defense Waste Processing Facility
Author:
Publisher:
Total Pages: 24
Release: 1990
Genre:
ISBN:

The information contained in this report is intended to supplement the original Environmental Impact Statement (EIS) for the Defense Waste Processing Facility (DWPF). Since the original EIS in 1982, alterations have been made to he conceptual process that reduce the impact to the groundwater. This reduced impact is documented in this report along with an update of the understanding of seismology and geology of the Savannah River Site. 6 refs., 2 figs., 2 tabs.

Defense Waste Processing Facility Radioactive Operations -- Part 2, Glass Making

Defense Waste Processing Facility Radioactive Operations -- Part 2, Glass Making
Author:
Publisher:
Total Pages: 12
Release: 1996
Genre:
ISBN:

The Savannah River Site's Defense Waste Processing Facility (DWPF) near Aiken, SC is the nation's first and world's largest vitrification facility. Following a ten year construction period and nearly 3 year non-radioactive test program, the DWPF began radioactive operations in March, 1996. The results of the first 8 months of radioactive operations are presented. Topics include facility production from waste preparation batching to canister filling.