The Major Projects Report 2009
Download The Major Projects Report 2009 full books in PDF, epub, and Kindle. Read online free The Major Projects Report 2009 ebook anywhere anytime directly on your device. Fast Download speed and no annoying ads. We cannot guarantee that every ebooks is available!
Author | : Great Britain. National Audit Office |
Publisher | : The Stationery Office |
Total Pages | : 340 |
Release | : 2009 |
Genre | : Political Science |
ISBN | : 9780102963380 |
This is a companion volume to the main report (HCP 85-I, ISBN 9780102963342)
Author | : Great Britain: National Audit Office |
Publisher | : The Stationery Office |
Total Pages | : 64 |
Release | : 2010-10-15 |
Genre | : Technology & Engineering |
ISBN | : 9780102965506 |
Central departmental decisions by the Ministry of Defence to try to balance the defence budget have reduced its cash-flow requirements in the short-term but at a long-term cost that represents poor value for money for the taxpayer. Not making realistic budgetary provision for all likely project outcomes and slowing down projects has resulted in a £3.3 billion increase in a single year, 2009-10, in the total cost of the 15 largest defence equipment projects. For the second successive year the cost performance on the majority of projects has been broadly stable and the rate of timescale slippage has also reduced significantly since last year and 98 per cent of Key Performance Indicators are expected to be met. The MOD did not make realistic budgetary provision for all potential costs, for example, on the Typhoon combat aircraft where the Department decided that it needed to spend £2.7 billion on the programme including the purchase of 16 additional aircraft to meet contractual agreements. It has slowed down projects such as the Queen Elizabeth Class aircraft carriers, leading to further project cost growth of £650 million. And, to address cost overruns, the Department has also reduced the number of items, and therefore capability, to be procured. The MOD recently undertook to report annually to Parliament on the affordability of its ten-year equipment plan, which should help deter the corporate practices which have adverse value for money implications.
Author | : Great Britain: National Audit Office |
Publisher | : The Stationery Office |
Total Pages | : 78 |
Release | : 2011-11-16 |
Genre | : Political Science |
ISBN | : 9780102976786 |
Action taken by the Ministry of Defence to balance its overall budget in the short term following the Strategic Defence and Security Review has contributed to a near £500 million in-year cost increase in the 15 largest defence projects. When coupled with previous cost growth, these projects are now £6 billion above forecasts made when the main investment decisions were taken. For the third successive year, central planning decisions taken by the Department, including delaying various projects, have had the biggest impact on cost growth, accounting for £237 million of the increase. Of this, £113 million relates to decisions to enhance capability. Macro-economic factors, such as adverse foreign exchange rates, accounted for £176 million of the increase. Cost overruns from project-specific technical issues accounted for £53 million. During 2010-11, there was a total increase of 30 months (with an average two months per project) in the forecast time to complete these projects and bring them into service. This brings the total delay on all 15 projects to 26.8 years. Long-term cost analysis by the NAO has shown that the difference between the approved and forecast costs of all projects which have had their main investment decision approved since 2000 is £10.6 billion (an 11.4 per cent increase). Additional costs have been avoided by reducing the amount of equipment the Department originally planned to buy. Had the Department not reduced equipment numbers, cost growth could have been between £18.2 billion and £19.4 billion (approximately 20 per cent) above the approved costs.
Author | : Great Britain: Parliament: House of Commons: Committee of Public Accounts |
Publisher | : The Stationery Office |
Total Pages | : 48 |
Release | : 2011-02-22 |
Genre | : Technology & Engineering |
ISBN | : 9780215556530 |
This report examines the Ministry of Defence's progress in meeting cost, time and performance targets for its 15 top-spending military equipment projects. The Committee has reported before that the defence equipment programme is unaffordable with commitments exceeding forecast budgets over a ten year period by £36 billion. The MoD's short term decisions to keep in year expenditure within voted limits and the need to understand the full cost implications of these decisions have damaging consequences. In this year alone the cost of the major projects rose by £3.3 billion and nearly £5 billion was lost by late cancellations. The scale of problems created by this financial imbalance masks the improved performance of the majority of projects against cost and budget. The Strategic Defence and Security Review (SDSR) offered the Department an opportunity to bring its plans into balance with the expenditure limits set in the Comprehensive Spending Review. Projects such as the Nimrod MRA4 and Sentinel aircraft have been cancelled, accepting greater operational risks in some areas and writing off nearly £5 billion of taxpayer's money. But implementing the SDSR will require further decisions and the renegotiation or cancellation of a significant number of existing contracts to make the programme affordable. The Department has a poor track record in taking such decisions on the well informed basis necessary to optimise value for money. Other projects examined in detail include the Queen Elizabeth Class aircraft carriers and the Typhoon aircraft.
Author | : Great Britain: Parliament: House of Commons: Defence Committee |
Publisher | : The Stationery Office |
Total Pages | : 194 |
Release | : 2010-03-04 |
Genre | : Technology & Engineering |
ISBN | : 9780215544223 |
The ability of the Defence Equipment and Support organisation within the Ministry of Defence (MoD) to deliver the equipment programme is overshadowed by the existence of a funding gap which the NAO estimates could be as much as £36 billion over the next ten years. Both the National Audit Office "Major Projects Report 2009" (HC 85-I, session 2009-10, ISBN 9780102963342) and Bernard Gray's "Review of Acquisition" for the MoD have confirmed that the MoD's ten year equipment programme is unaffordable. Furthermore the MoD's practice of delaying projects so as to reduce costs in the early years of a programme is adding to overall procurement costs and so further increases the funding gap. The MoD has apparently made no attempt to calculate the full extent of the costs of delays and it has taken decisions to delay projects without understanding the full implications of those decisions. The report examines: progress on the many key programmes; defence research spending (declining from £540 million in 2007-08 to £471 million in 2009-10 and will decrease further in 2010-11 to £439 million); the response to and implementation of the Gray report; balancing the equipment programme and the use of regular Strategic Defence Reviews to maintain an up-to-date strategic context for the equipment programme; clarifying roles and accountabilities, including better leadership and decision-making; injecting key skills and tools into DE&S.
Author | : Great Britain. National Audit Office |
Publisher | : The Stationery Office |
Total Pages | : 36 |
Release | : 2008 |
Genre | : Technology & Engineering |
ISBN | : 9780102954425 |
The Major Projects Report 2007 covers cost, time and performance data for military equipment projects in the year ended 31 March 2008. 20 of the largest projects are examined where the main investment decision has been taken by the Ministry of Defence (the MoD) along with ten projects still in the Assessment Phase. Six projects are new to this report: future lynx; modernised target acquisition designation sight/pilots night vision sensor; naval extrememly high frequency/super high frequency satellite communication terminals; Typhoon future capability programme; advanced jet trainer project and project Eagle
Author | : Great Britain: Parliament: House of Commons: Committee of Public Accounts |
Publisher | : The Stationery Office |
Total Pages | : 36 |
Release | : 2010-03-23 |
Genre | : Technology & Engineering |
ISBN | : 9780215544995 |
This report examines whether the Ministry of Defence's (MoD) governance and budgeting arrangements are fit for purpose and whether it understands the serious implications of reprioritising projects after committing to them. The Committee identifies the serious consequences of failings in the governance and budgetary processes. Even using the MoD' own, over-optimistic estimates the defence budget is unaffordable by some £6 billion. The exact size of the gap is dependent on the assumptions made about future funding, but the gap could easily be £36 billion. Intentional decisions to delay some projects have increased total procurement costs and represent economies of the short term and overall are poor value for money on the specific projects affected, the report said. The decisions were taken as part of a wider package to try to make the defence programme affordable over the next few years. They account for two thirds of the £1 billion of cost increases on projects in the last year. Crucially, they mean the Armed Forces will not get the operational benefits of new capabilities as quickly as expected. Decisions to delay projects, change requirements and reduce the numbers of equipments being procured adversely affect the MoD's ability to secure value for money from its commercial partners. The MoD is in the strongest negotiating position with industry before it places a contract. Slowing projects down once started almost inevitably increases their costs and takes pressure off contractors to become more efficient.
Author | : Tony Prosser |
Publisher | : OUP Oxford |
Total Pages | : 1187 |
Release | : 2014-03-13 |
Genre | : Law |
ISBN | : 0191027405 |
There has been little analysis of the constitutional framework for management of the UK economy, either in constitutional law or regulatory studies. This is in contrast to many other countries where the concept of an 'economic constitution' is well established, as it is in the law of the European Union. Given the extensive role of the state in attempting to resolve recent financial crises in the UK and elsewhere in Europe, it is particularly important to develop such an analysis. This book sets out different meanings of an economic constitution, and applies them to key areas of economic management, including taxation and public borrowing, the management of public spending, (including the Spending Review), monetary policy, financial services regulation, industrial policy (including state shareholdings) and government contracting. It analyses the key institutions involved such as the Treasury and the Bank of England, also including a number of less well-known bodies such as the Office for Budget Responsibility. There is also coverage of the international context in which these institutions operate especially the European Union and the World Trade Organisation. It thus provides an account of the public law applying to economic management in the UK. This book also adopts a critical approach, assessing the degree to which there is coherence in the arrangements for economic management, the degree to which economic policy-making is constrained by constitutional norms, and the degree to which economic management is subject to deliberation and accountability through Parliament, the courts and other institutions.
Author | : Robert Self |
Publisher | : Routledge |
Total Pages | : 325 |
Release | : 2022-06-16 |
Genre | : History |
ISBN | : 1000600238 |
This book explores the process by which defence policy is made in contemporary Britain and the institutions, actors and conflicting interests which interact in its inception and continuous reformulation. Rather than dealing with the substance of defence policy, this study focuses upon the institutional actors involved in this process. This is a subject which has commanded far more interest from public, Parliament, government and the armed forces since the protracted, bloody and ultimately unsuccessful British military involvement in Iraq and Afghanistan. The work begins with a discussion of two contextual factors shaping policy. The first relates to the impact of Britain’s ‘special relationship’ with the United States over defence and intelligence matters, while the second considers the impact of Britain’s relatively disappointing economic performance upon the funding of British defence since 1945. It then goes on to explore the role and impact of all the key policy actors, from the Prime Minister, Cabinet and core executive, to the Ministry of Defence and its relations with the broader ‘Whitehall village’, and the Foreign Office and Treasury in particular. The work concludes by examining the increasing influence of external policy actors and forces, such as Parliament, the courts, political parties, pressure groups and public opinion. This book will be of much interest to students of British defence policy, security studies, and contemporary military history.
Author | : Great Britain: National Audit Office |
Publisher | : The Stationery Office |
Total Pages | : 412 |
Release | : 2013-01-10 |
Genre | : Technology & Engineering |
ISBN | : 9780102980592 |
In respect of its largest defence projects there are early signs that the Ministry of Defence has begun to make realistic trade-offs between cost, time, technical requirements and the amount of equipment to be purchased. Nevertheless, the continuing variances to cost and time show the MOD needs to do consistently better. This report, which gives a progress review of the 16 largest defence projects, shows that in the last year there has been a total forecast slippage of 139 months and increase in costs of £468 million. This means that, since the projects were approved, costs have increased by £6.6 billion (around 12 per cent more than the planned cost) and the projects have been delayed by 468 months, taking almost a third longer than originally expected. It would be unrealistic to expect MOD and industry to identify every risk at the start of technically challenging projects. However, the continuing problems indicate that MOD has more to learn from historic. The MOD is accepting the capability risk and some wider costs resulting from these project delays and is having to make difficult decisions about long-term capabilities. The MOD has made a significant investment in new and upgraded helicopters to address the shortfall identified in the NAO's 2004 report. The MOD has also spent £787 million on air transport and air-to-air refuelling aircraft to support current operations and address capability gaps, such as those caused by the previously reported delays to the A400M transport aircraft. However, capability gaps remain